Christiansted Underground Project
(Monday, December 10, 2012)
Christiansted Underground Phase 2 Project
Design and Construction Weekly Report
12/3/12 to 12/8/12
Strand St. Intersecting/ Prince St. / King Cross St. / Queen Cross St. / Stand Lane.
Goals: Total Primary Trench and Primary Ducts = 1800 Ft
12-3-12
- [J Benton Construction] Continue to work on Secondary trench near library
- [J Benton Construction] Encountered concrete under the asphalt on King Cross Street heading towards Water Gut road.
- 12-4-12
- [J Benton Construction] Finished secondary trench work for the library.
- [J Benton Construction] Begin to demolish 4” thick concrete found under the asphalt on King Cross Street heading toward Water Gut road.
- [J Benton Construction] Installed 255 FT of primary ducts in primary trench on King Cross Street heading towards Water Gut road. The ducts were covered with concrete.
- 12-5-12
- [J Benton Construction] Installed 145 FT of primary ducts in primary trench on King Cross Street heading towards Water Gut road.
- [VIWAPA] Office Work. Attended J Benton Construction Weekly Meeting in Orange Grove.
- [J Benton Construction] Installed secondary conduits for Holger Danske Hotel and Jones Marina.
-
12-6-12
- [J Benton Construction] Worked a night shift to in order to let waterline and electric conduits cross over King Cross Street
- [J Benton Construction] Worked during the day to form concrete pad for the Gov’t Parking Lot. Pad however needs to reform.
- 12-7-12
- [VIWAPA] Office Work. Attended meeting with members of CRRA to discuss and listening to concerns with the C-sted Underground Phase 2 Project
- [J Benton Construction] Saw cut on Strand Street to prepare road for work Scheduled on Monday
- 12-1-12
- Work Suspended to have all roads open for the Boat Parade and other activities.
Milestone: Total Primary Ducts Installed: = 845 Ft
Percentage complete: = 47.0%