Christiansted Underground Phase 2 Project Weekly Report (12/17/12 to 12/21/12)

(Friday, December 28, 2012)

Design and Construction Weekly Report

12/17/12 to 12/21/12

Strand St. Intersecting/ Prince St. / King Cross St. / Queen Cross St. / Stand Lane.

Goals: Total Primary Trench and Primary Ducts = 1700 Ft

  • 12/17/12
    • [J Benton Construction] Work resumed on Strand Street and Queen Cross Street with primary duct installation continuing.
    • [J Benton Construction] Tied new water line to the existing water line valve.
  • 12-18-12
    • [J Benton Construction] Trenched, laid and covered 75 FT of primary ducts on Strand Lane
    • [J Benton Construction] Continue to saw cut road on Stand Lane
  • 12-19-12
    • [J Benton Construction] Trenched, laid and covered 75 FT of primary ducts Strand Lane
    • [VIWAPA] Office Work. Attended J Benton Construction Weekly Meeting in Orange Grove.
  • 12-20-12
    • [J Benton Construction] Trenched, laid and covered 50 FT of primary ducts on Stand Lane
    • [J Benton Construction] Cleaned up site and work zone for the weekend.
  • 12-21-12
    • [VIWAPA] Office Work. Work will resume on 12-27-12

Milestone: Total Primary Ducts Installed: = 1345 Ft

Percentage complete: = 79.11%

> Download Report in PDF Format (additional photos included)