Week #11 Update#2Csted Detours on Wednesday:Crews Paving on Strand St. from King Cross to Prince & King Cross from Watergut Rd. to King St.

(Tuesday, January 15, 2013)

On Tuesday through Friday, January 15 to 19,  Virgin Islands Water and Power Authority contractor   J. Benton Construction will begin repaving the streets where underground electric and water lines have been installed recently to improve reliability of service in Christiansted town. 

On the four days of repaving, work will begin at 4 a.m. and the roads will reopen by no later than 3:30 p.m, each day.  Detours will be available and flaggers will assist in traffic directions.
 
On Tuesday, Strand Street between King Cross and Prince Streets will be closed to vehicular traffic. The government parking lot can be accessed from Watergut Road. 
 
On Wednesday,  Strand Street between King Cross and Prince Streets (to be completed) & King Cross Street from Watergut Road to King Street

On Thursday,  Strand Street from King Cross Street to Queen Cross Street will be closed to vehicular traffic.

On Friday, from the intersection of Strand and Queen Cross Streets down Queen Cross Street to the Boardwalk and along Strand Lane will be closed to vehicular traffic.
 
 
Also on Wednesday, underground work will continue on King Street . Work crews will be trenching, laying conduits and covering up the open trench daily from Prince Street to King Cross Street until that section of King Street is completed.  Lower areas of King Street and Christiansted town can be accessed from the Christiansted Bypass..
 

Instructions:

For information email communications@viwapa.vi or call 340-773-2250 ext. 4085 or 2050