St. Thomas-St. John, U.S. Virgin Islands (August 27, 2026) — The Virgin Islands Water & Power Authority (“WAPA” or “the Authority”) advises customers on the eastern portion of St. Thomas and throughout St. John that the planned outage for the Feeder 13 Bypass Project is scheduled for Sunday, August 30, from 11:00 a.m. to 6:00 p.m., weather permitting.
The outage will affect the following feeders:
Feeders 9E, 8E, 7E, 9C, 7C, 10B, portion of 7B (Raphune Hill to Tabor & Harmony), and the Mall.
The scheduled work will support the remaining project activities needed to prepare the new bypass for energization and operation. Once energized, the bypass will give WAPA greater flexibility in managing the electric system and responding to system needs.
The Feeder 13 Bypass Project represents approximately two years of planning, engineering, and construction, supported through $17 million in FEMA funding. The bypass will create an alternate transmission path during emergencies, maintenance, or equipment issues to the Feeder 13 underground transmission line. This capability will support more reliable service for approximately 37,600 customers across the St. Thomas-St. John district.
This significant milestone reflects WAPA’s continued efforts to strengthen the electric system and improve its reliability and resilience. WAPA appreciates the understanding and continued support of customers and the community as this important project moves toward completion.
The Virgin Islands Water and Power Authority Communications Department is committed to reaching, informing, and connecting with the youngest members of the community to the eldest through meaningful, transparent, and effective communication.