WAPA Restores Service Following Rotating Outages; Additional Generation Remains a Priority

Oct 18, 2026

U.S. VIRGIN ISLANDS (Oct. 18, 2026) — The Virgin Islands Water and Power Authority (“WAPA” or “the Authority”) ended generation-related rotating outages in the St. Thomas–St. John district Saturday at approximately 2:55 p.m., following separate equipment failures that reduced available generation below customer demand.

The outages began Thursday around 4:00 p.m. following the loss of the Wärtsilä Phase 2 units. A separate failure occurred Friday around 4:30 p.m., when GE Unit 27 tripped offline. With insufficient backup generation available, both events created outages. Due to lack of backup generation, delayed restoration of Unit 27 resulted in rotating outages.

“We understand the frustration these interruptions cause for families and businesses. We are progressing toward a system that can better withstand these events,” said WAPA CEO and Executive Director Karl Knight. “Adding additional generation to the Randolph Harley Power Plant remains a priority.”

WAPA is advancing temporary and permanent generation at both power plants with the FEMA Prudent Replacement Program led by the Office of Disaster Recovery, while working to return Units 23 and 15 and Wärtsilä 5 to service on St. Thomas. These efforts are moving forward simultaneously to increase available capacity as quickly as practicable. Until sufficient backup generation is in place, the loss of any operating unit may continue to leave the district short of the power needed to serve all customers.

Separately, WAPA line crews are addressing an isolated outage affecting four customers in West Caret Bay and a portion of customers Northside, St. Thomas. On St. Croix, a vehicle collision with a utility pole Saturday affected Feeder 9B. Trees in the line caused an approximately 90-minute outage on Feeder 4A this morning, which crews addressed. These localized distribution issues are separate from the generation-related outages in the St. Thomas–St. John district.

WAPA recognizes the strain repeated interruptions place on the community. The immediate priority is to increase available generation while pursuing the sustained investment needed to strengthen the system for the long term.

###