Divider

Article Details

WAPA Board Approves Changes To Mitigation Projects, St. Croix Water Line Rehab Project Extension, And Contract For Project Management Services

May 30, 2020

 

logo-small

The Virgin Islands Water and Power Authority
Corporate Communications
NEWS RELEASE
Contact: Jean P. Greaux, Jr., Director of Corporate Communications
340-774-3552 extension 2147 or 340-244-7330
communications@viwapa.vi / www.viwapa.vi

May 30, 2020

 

WAPA BOARD APPROVES CHANGES TO MITIGATION PROJECTS, ST. CROIX WATER LINE REHAB PROJECT EXTENSION, AND CONTRACT FOR PROJECT MANAGEMENT SERVICES

 

      The governing board of the Virgin Islands Water and Power Authority on Thursday took favorable action on several items pertaining to long-term mitigation projects aimed at hardening the utility’s electric and water systems.

      The board awarded a $5.9 million underground project management contract to FX Bonnes, a company that has done work with WAPA in the past. The company will provide construction management services for projects in both districts to underground aerial transmission and distribution lines making for speedier service restoration from windstorm events. At the completion of the undergrounding projects, WAPA will make underground electrical service available to more than 50% of its customers. 

      Along the same lines, the board approved a 30-day extension and a cost increase to an existing contract for the reconstruction of the East End Electrical Substation on St. Thomas. The facility, damaged in the 2017 hurricanes, is essential to the safe and reliable functioning of the electrical grid, specifically, electrical transmission lines to St. John, and distribution lines to Feeders 7D, 9D, and Ridge Road Feeder on St. Thomas. The project was designed initially to replace hurricane damaged 38kV switchgear in a new reinforced concrete building at the site in Estate Nazareth and, at a future date, add a second building to house a 15kV switchgear. Changes to the building design were required to accommodate alterations in equipment type and configuration, and to add the 15kV switchgear. By expanding the size of the building and adding the 15kV switchgear, WAPA avoided costs associated with constructing a second building, a savings of approximately $800,000. An additional building will only be required should there be a need for a 69kV switchgear at the substation site. The need for a 69kV switchgear is presently being evaluated. 

In other action, the board approved:

  • An increase in the contract term of 210 days for phase two of the Frederiksted Waterline Rehabilitation Project. Delayed payment of mobilization fees by WAPA, and the effect of COVID-19 on the shipment of materials delayed the project. The contract was extended to January 2021.
  • The rescinding of a contract award for the container port underground construction project on St. Croix to allow for additional details to be provided to all responsive bidders and for the submission of amended proposals. The revised proposals will then be reviewed by WAPA staff and resubmitted to the governing board for consideration. 
  • The execution of a one-year, $240,000 contract, with Sustainable Capital Advisors, LLC to provide municipal advisory services as regards to capital planning, budget, and financing alternatives among other things.
  • A cost increase in existing contracts with security guard companies whose personnel will perform temperature screenings for employees, contractors, and visitors at various WAPA facilities territory-wide.

      In his monthly report, Executive Director Lawrence J. Kupfer told board members of territorial power generation in April being at the same level as March, approximately 68 megawatts. “We have seen demand slowly returning to pre COVID-19 levels in recent weeks which could be attributed to either increasing electrical demand as days have gotten a bit warmer or the reopening of some businesses.”

     Fuel markets, he said, are still somewhat unstable and LPG prices have edged up a bit. Today, the price spread between both fuel types has LPG about 15% below the cost of oil. 

     Kupfer reported that St. Thomas generating Unit 15 is back in service. “We had some issues with it, we received assistance from Limetree Bay with a replacement breaker and along with another breaker from a WAPA unit on St. Croix, Unit 15 was returned to service on propane.” Unit 23, the largest generator on St. Thomas, is being dispatched regularly, as fuel issues have been resolved.  Water inventories are good, and the distribution systems are operating normally. “We have seen a bit of a dry spell, but we have managed to maintain inventory,” Kupfer said.

     Board members present included Chairman Anthony D. Thomas, Vice Chairman Noel Loftus, Secretary Juanita Young, Directors Kyle Fleming and Joel Lee, Cheryl Boynes Jackson, Elizabeth Armstrong, Jed JohnHope, and Hubert Turnbull.

 

# # #

 

About WAPA: The Virgin Islands Water and Power Authority is an autonomous agency of the Virgin Islands Government which produces and distributes electricity and drinking water to residential and commercial customers in the territory. WAPA was created by the Fifth Legislature of the Virgin Islands in 1964 through Act No. 1248. Today, WAPA generates electrical power at production plants on St. Thomas and St. Croix and distributes electrical service through smart grids to customers on St. Thomas, St. Croix, St. John, Hassel Island, and Water Island. Potable water is distributed to almost 13,000 customers through water lines and standpipes. WAPA also has the responsibility of installing and maintaining streetlights.